Day 1 Assessment
1. Today is Friday 12 June. The scheduling tool goes live Monday 3 August, a date the ward's rota fixes. Forty ward clerks will key admissions data on it every shift; six department heads will pull one report a month. The ward's seat on the requirements group fell vacant in January and was never filled; the heads signed the requirements in March. The build has been in test since 5 June. UAT starts Monday 29 June, scripted from the signed requirements, with a participant list of the six heads and two IT staff. Until UAT the team absorbs changes inside the sprint; the UAT plan is under configuration control, and changes to it take the change board a median of 15 working days. What is the best use of the time before UAT?